UPGRADE_WORK_MOVED

`nextly upgrade` was run for the database work it used to do, which `nextly migrate` and `nextly i18n:convert-zoned-dates` now do, so it changed nothing.

Cause

nextly upgrade was run for the database work it used to do, which nextly migrate and nextly i18n:convert-zoned-dates now do, so it changed nothing.

Earlier releases used nextly upgrade to bring an existing database up to date. That work has moved. nextly migrate now moves the migration records of an earlier release, brings Nextly's own tables up to date, hashes passwords stored before this release, removes passwords kept in version history and converts roles holding a retired manage permission. nextly i18n:convert-zoned-dates converts translated date columns kept with a time zone. nextly upgrade now moves the project's Nextly packages to a release. The flags of the earlier work (--confirm-backed-up, -f/--force, --reconcile-core, --target-table-name, --force-unlock, --accept-data-loss) still parse, and a run with one opens no database, moves no package, changes nothing and exits 1, so a deploy script that still passes one fails here instead of doing something else.

Fix

  • Replace nextly upgrade in your deploy with nextly migrate. Where no terminal is attached, pass --backup-confirmed once the database is backed up; the flag is ignored when there is nothing to change.
  • A development database with no migrations gets the same work from nextly db:sync.
  • If a start or nextly migrate names a date column with a time zone, run nextly i18n:convert-zoned-dates once the release serves every instance.

Example

✗ `nextly upgrade` no longer changes the database, and changed nothing.
  Why:  `nextly migrate` now moves the migration records of an earlier release, brings Nextly's own tables up to date, hashes passwords stored before this release, removes passwords kept in version history and converts roles holding a retired manage permission. `nextly i18n:convert-zoned-dates` converts translated date columns kept with a time zone. `nextly upgrade` moves the project's Nextly packages to a release, and takes none of the flags that work had.
  Next: Run `nextly migrate` (`nextly migrate --backup-confirmed` where no terminal is attached). Once the release serves every instance, run `nextly i18n:convert-zoned-dates` if a start or `nextly migrate` named such a column. To move the packages, run `nextly upgrade` without the flag.
  Docs: https://nextlyhq.com/docs/cli/errors/upgrade-work-moved  (UPGRADE_WORK_MOVED)